Free check · model-code sourced
Replacing the AC? That needs a permit.
The model code most US jurisdictions adopt (2021 IRC R105.1) requires a permit to “erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system” — like-for-like included. Check your job below; the checker answers only what the code answers, and says so when it can’t.
Verdicts answer only what the model building code answers (2021 IRC R105.1 / R105.2) — local amendments vary, and no national permit-requirement database exists from any government source. When in doubt, the answer is always your local building department.
The two clocks that expire permits
Model code: 180 days to start work, 180 days of inactivity kills it (IRC/IBC 105.5). California: 12 months to commence (AB 2913). Florida: alive only 180 days from each passing inspection (FBC 105.4.1) — expired means a new permit. Extensions exist, but only requested in writing, filed before expiration.
The open-permit resale trap
A permit that never got its final inspection stays open — and title companies find it when the property sells, years later, as the buyer’s objection or the seller’s bill. The rule that avoids all of it: no job is finished until the final inspection passes.
Sources — and the honest limit
2021 International Residential Code R105.1/R105.2 and IRC/IBC 105.5 (model text) · California AB 2913 (2018) · Florida Building Code 105.4.1 and F.S. 553.79 · LADBS express-permit bulletin P/GI 2026-003 · Houston Permitting Center · CSLB owner-builder guidance. The limit: permitting is local — no national government database of requirements exists, local amendments override model text, and unincorporated areas (notably in Texas) may have no mechanical permit requirement at all. Your building department is always the final word.
We track these clocks so nobody has to remember them
Morthn runs the back office for service businesses. Our platform tracks every job’s permit against its jurisdiction’s actual clock — commencement, inactivity, Florida’s inspection-reset — chases the renewals before the deadlines, and refuses to let a job archive without its final inspection, because the open permit is always found eventually.